Project Summary: Phase II of the restoration of the original design elements of this historic building, including renovations to 4,500 square feet of interior space, system upgrades, and exterior renovations.
Contract Value: $1.1M
Completion: June, 2004
Owner: Corinthian Yacht Club
Architect: Erling Falck
Following its successful reconstruction of the dining and function portion of the building over the winter of 2002-2003, starting in October of 2003 DeIulis Brothers continued work on the remainder of the building, providing necessary structural stability, installing new exterior siding and roofing, upgrading building systems, improving access and refurbishing the interior spaces. DeIulis Brothers used its own forces to complete the key phases of work, including demolition, shoring, masonry and carpentry work on the project. Items of note included the following:
Construction of new handicap ramp to blend with the exterior design features
Reconstruction of front entrance, lobby and reception area
Detailed interior finishes and reconstruction of main staircase
Installation of elevator and new handicap bathrooms